Change Orders in Construction: How to Document, Price and Get Paid

How to manage change orders in construction: the step-by-step process, what to put on the form, how to price a change and how to make sure you get paid.

DataGo's teamUpdated Nov 16, 2026 · 9 min read
Contact us

Quick answer: A change order is a written agreement that modifies a construction contract's scope, price or schedule after work has started. To protect your margin, document every change in writing, price it with all direct costs, overhead, profit and schedule impact, and get it approved before the work begins. Unapproved, undocumented changes are one of the most common ways contractors lose money on a job.

It usually starts with a simple request on site: "Can you move that wall a foot?" "Let's upgrade the fixtures." "While you're here, can you add one more outlet?" The crew wants to keep the client happy, so they do it. Weeks later, at billing time, nobody remembers exactly what was agreed, how much it was supposed to cost, or whether it was ever approved.

Managing change orders in construction is one of the clearest ways to protect your margin, and one of the easiest to get wrong. This guide explains what a change order is, what causes them, the step-by-step process, what every change order form should include, how to price a change, and how to make sure approved changes actually reach your invoice.

What is a change order?

A change order is a written document, signed by the owner and the contractor (and, on many projects, the architect), that modifies the original contract. It typically changes one or more of three things:

  • Scope: work is added, removed or modified.
  • Price: the contract sum goes up or down.
  • Time: the completion date moves.

On projects that use American Institute of Architects (AIA) contracts, the general conditions (AIA Document A201) set out how changes in the work are handled, and AIA Document G701 is a standard change order form. Smaller residential and commercial jobs often use simpler forms, but the principle is the same: no change to scope, price or time without a written, approved document.

What causes change orders?

CauseExampleTip
Owner-requested changesUpgraded finishes, layout changes, added scopePrice before you build; never work on a verbal request
Design errors or omissionsA conflict between drawings, a missing detailDocument the issue with photos and dates as soon as you find it
Unforeseen site conditionsRock in an excavation, rot behind drywall, hidden utilitiesCheck your contract's notice requirements and report quickly
Code or permit requirementsAn inspector requires additional workKeep inspection reports with the change request
Schedule accelerationThe owner asks to finish earlierPrice overtime, extra crews and added supervision

Who pays depends on the cause and on your contract. That is why documentation from the field matters so much: it is the evidence that supports your request.

Change order vs. change directive vs. field order

DocumentWhat it isWhen it's used
Change orderSigned agreement on scope, price and timeBoth parties agree on the change and its cost
Construction change directiveWritten instruction to proceed before price or time is agreedWork can't wait, but the cost is still being negotiated
Field order or minor changeSmall adjustment with no change in price or timeMinor clarifications in the field

On AIA projects, the construction change directive is AIA Document G714. If you receive one, track every cost related to that work carefully, because those records will support the final price.

The change order process, step by step

  1. Identify the change. Anyone on site who receives a request or finds a condition that affects scope should flag it the same day.
  2. Document it. Record what was requested, by whom, when and where, with photos and references to the drawings.
  3. Notify the owner in writing. Follow the notice period in your contract; many contracts require notice within a set number of days.
  4. Price the change. Calculate labor, materials, equipment, subcontractors, overhead, profit and schedule impact.
  5. Submit the change order. Send a clear proposal with scope, price, time impact and a deadline for approval.
  6. Get written approval before starting. If the work truly can't wait, ask for a written directive to proceed.
  7. Update the budget and schedule. Add the approved change to the job budget so costs are tracked against it.
  8. Bill the change. Include approved change orders in your next invoice or pay application.

What every change order form should include

FieldWhy it matters
Project name and numberLinks the change to the right job
Change order number and dateKeeps a clear log of every change
Description of the changeDefines exactly what is added, removed or modified
Reason for the changeSupports who should pay
Reference to drawings or specificationsRemoves ambiguity
Cost breakdownLabor, materials, equipment, subcontractors, markup
Schedule impactDays added to the completion date, if any
Revised contract sumShows the new total after the change
Signatures and datesProves approval

Keep one numbered log of all change orders for each job, including pending, approved and rejected ones. It becomes your best tool in any billing discussion.

How to price a change order

A change order should cover the full cost of the change, not just materials and labor hours.

  1. Direct labor at the burdened rate (wages plus payroll taxes, workers' compensation, insurance and benefits), not the base wage.
  2. Materials, including delivery and expected waste.
  3. Equipment rental or usage.
  4. Subcontractor costs, including their markup.
  5. Overhead and profit, at the markup allowed by your contract.
  6. Schedule impact: extra supervision, extended rentals or general conditions if the job runs longer.

An illustrative example: an owner asks to add three windows to a remodel.

ItemCost
Materials (windows, trim, flashing)$2,400
Labor: 24 hours × $40 burdened rate$960
Subcontractor (electrical adjustment)$600
Subtotal$3,960
Overhead and profit (15%, as allowed in this example contract)$594
Change order total$4,554
Schedule impact+2 working days

If the crew had done this work on a verbal request and the cost had never been billed, the contractor would have lost $4,554, almost all of it straight from the job's profit.

Handling verbal requests in the field

Most unbilled changes start as a friendly conversation on site. Give your superintendents and crew leads a simple rule: "We'd be happy to do that. Let me write it up so we can get it priced and approved."

Then make it easy to follow:

  • Log the request immediately, from a phone, with photos.
  • Tell the crew not to start until the change is approved, unless there's a safety issue.
  • Route it to the person who prices changes the same day.

This protects the relationship with the client as much as the margin: clear changes avoid surprises on the invoice.

Tracking change orders in job costs and billing

An approved change order isn't finished until it shows up in two places:

  • Your job cost report. Add the change to the budget, with its own cost code if possible, so you can see whether the change itself made or lost money.
  • Your billing. On commercial projects that use AIA pay applications (Documents G702 and G703), approved change orders are added to the contract sum and billed as the work is completed.

If you track costs and billing separately from your change order log, approved changes slip through. Keeping them in the same system closes that gap. For more on tracking costs by job, see our guide to construction job costing.

Change orders by type of contractor

Changes look different depending on your trade, and so do the details you need to capture:

  • Roofing contractors: hidden deck damage, extra layers to tear off or additional flashing details are the most common changes. Photograph the condition before you continue and price it by square or by sheet of decking.
  • Remodelers and interior fit-out firms: owner-driven changes to layouts, finishes and fixtures are constant. Agree on a change order process at the kickoff meeting and include selection deadlines so late choices don't delay the job.
  • Painting contractors: added rooms, extra coats, color changes after work has started or surface repairs discovered during prep. Price by square foot and note any extra prep labor separately.
  • General contractors: changes often flow from the owner or architect to several subcontractors at once. Collect sub pricing quickly, add your markup and keep a single log for the whole project.
  • Custom fabricators: changes to dimensions or materials after shop drawings are approved can mean rework. Confirm changes in writing before releasing anything to production.

Whatever the trade, the rule doesn't change: document it, price it, get it approved and bill it.

Common change order mistakes

  • Starting work on a verbal approval.
  • Missing contractual notice deadlines, which can weaken your right to be paid.
  • Pricing labor at base wage instead of the burdened rate.
  • Forgetting schedule impact and extended general conditions.
  • Not updating the budget, so the change's real cost is never measured.
  • Billing changes late, sometimes months after the work was done.

How Prisma ERP helps you manage change orders

Prisma ERP is a project-based management platform for contractors that run multiple jobs with field crews: construction, roofing, interior fit-out and remodeling, custom manufacturing and painting. DataGo's is a partner that brings Prisma ERP to contractors in the United States, Mexico and Latin America.

For change orders, Prisma ERP helps you:

  • Document changes before the work starts through work orders with defined scope.
  • Keep the job budget current, since changes are tied to each project's baseline from the original estimate.
  • Track crew time and materials used on each job, with crew scheduling, GPS check-in and materials tracking.
  • See the impact on margin in a real-time dashboard for every job.
  • Bill approved work through invoicing integrated with QuickBooks.

Frequently asked questions

Can a contractor refuse a change order?

It depends on the contract. Many contracts allow the owner to order changes within the general scope of the work, with an adjustment in price and time. Review your contract terms and get legal advice for significant disputes.

What happens if the owner won't sign a change order?

Keep documenting the work and costs, follow the dispute process in your contract, and avoid starting the work without written direction. On AIA projects, a construction change directive can authorize work while the price is negotiated.

How long do I have to submit a change order?

Check your contract. Many contracts set specific notice periods for claims and changes, and missing them can limit your ability to be paid.

Do small residential jobs really need written change orders?

Yes. A one-page form or a documented approval by email or text, with the description, price and signature or written "approved," is enough for most small jobs. What matters is that both sides agree on the change and the price before the work starts.

Who should approve change orders?

Whoever the contract names, usually the owner, and on many projects also the architect. Make sure the person signing has the authority to approve changes in price and time.

Conclusion: no change without a signature

Handling change orders in construction well is less about forms and more about discipline: document every change the day it happens, price it completely, get it approved before the work starts and make sure it reaches your invoice. Contractors who follow that routine protect their margin and their client relationships at the same time.

Losing money on changes that never get billed?

Contact DataGo's. We bring Prisma ERP to contractors in the US, Mexico and Latin America. Tell us about your projects and we'll show you how to document changes, track costs and bill approved work from one platform.

Prefer to pick a time? Book directly.

References

  • American Institute of Architects. AIA Document A201, General Conditions of the Contract for Construction.
  • American Institute of Architects. AIA Document G701, Change Order.
  • American Institute of Architects. AIA Document G714, Construction Change Directive.
  • American Institute of Architects. AIA Documents G702 and G703, Application and Certificate for Payment.